Capital Campaign committee meets and selects Fairmount ventures as the Feasibility Study Consultants for the capital campaign

4/3 -  2nd Interview with Fairmount Ventures, Feasibility Study Consultants for the capital campaign

4/10 - Capital Campaign committee meets and selects Fairmount ventures as the Feasibility Study Consultants for the capital campaign

4/19 2nd construction cost estimate comes in at $21,654,000 - still too high and further cost reductions need to be made.

4/26 -  New Building Committee conference call with Lukmire Architects to refine the design of the new library in order to reduce the construction costs.

4/15 - The Board affirmed the selection of Fairmount Ventures, Philadelphia, as the library feasibility consultant.

4/17 -  Bike Kennett donates and installs a bike rack at the Kennett Library


08/22/2018 03:40:00 pm

Board + Building
Monthly updates about managing our library and preparing to build a new library center